Injection Molding: New Mold Trial—Will It Run 24/7?Use this nine-step process to make sure you’ll be making good parts after a successful trial. But even then, be prepared for some hiccups.
Columns Post: 12/1/2017
JOHN BOZZELLI
Related Topics:
The arrival of a new tool always generates
a certain level of excitement. Often it’s late and
everyone is in a rush to make “good” parts to show the client. The client may be there with you,
so the pressure is on. You need to look like you know what you’re doing. You are hoping “Murphy”
is asleep, because if he isn’t—well, you know by now—what can go wrong will go wrong.
everyone is in a rush to make “good” parts to show the client. The client may be there with you,
so the pressure is on. You need to look like you know what you’re doing. You are hoping “Murphy”
is asleep, because if he isn’t—well, you know by now—what can go wrong will go wrong.
The history and culture of our industry has
been to pull out every trick possible to work around—
not solve—any problems with the design, resin, tooling, machine, etc. Having issues with burns?
No problem, just slow the injection rate. Getting flash, color streaks, blush, shrink, warp, etc.?
Don’t worry, just spend hours on profiling, fixturing, trimming, changing temperatures, and other
tricks of the trade to get around these problems.
not solve—any problems with the design, resin, tooling, machine, etc. Having issues with burns?
No problem, just slow the injection rate. Getting flash, color streaks, blush, shrink, warp, etc.?
Don’t worry, just spend hours on profiling, fixturing, trimming, changing temperatures, and other
tricks of the trade to get around these problems.
If this is the way you go about things,
likely you’ll have molded a few good parts to show the client,
and the pressure will be off for some period. A short-term fix—but ultimately Murphy will awaken,
realize he has lulled you into a false sense of security, and will look to extract his toll.
and the pressure will be off for some period. A short-term fix—but ultimately Murphy will awaken,
realize he has lulled you into a false sense of security, and will look to extract his toll.
Injection molding is a thermal cycle, and
some molds can take a long time to equilibrate.
You’ll often run into problems after those
first few parts are made because the trial was too short.
Maybe you had other tools to trial, or a production problem to solve, so you did the best you could in
the time allotted. You made acceptable parts covering the basics, such as the following (each mold is
unique and may have special needs):
Maybe you had other tools to trial, or a production problem to solve, so you did the best you could in
the time allotted. You made acceptable parts covering the basics, such as the following (each mold is
unique and may have special needs):
Ensure shorts will be ejected. Any mold
will make shorts periodically and they need to be
ejectable. The production hours lost due to
“Crusty” the operator digging out shorts easily
justifies the extra costs involved. And
this does not count the tool damage done by a frustrated
operator that accidentally slipped with the drywall screw, ejector pin, etc., while digging out the
short shot.
operator that accidentally slipped with the drywall screw, ejector pin, etc., while digging out the
short shot.
Check venting, specifically that 30% of the
parting line is vented to the right depth, with the proper
vent land, etc. Make sure you have no burning or gloss variations due to trapped gas.
vent land, etc. Make sure you have no burning or gloss variations due to trapped gas.
Confirm the mold has, on its side, clear
cooling diagrams for the hook-up of all water lines with the
required flow rates. Document and check flow rates and temperatures and ensure there are no
restricted flow paths.
required flow rates. Document and check flow rates and temperatures and ensure there are no
restricted flow paths.
If you are running a hot-runner mold, make
sure it has a clear diagram on the hot half, showing the
sprue, manifold, drops, etc. with each heater zone clearly called out.
sprue, manifold, drops, etc. with each heater zone clearly called out.
Perform a Scientific Molding trial to
optimize fill time, pack and hold (via gate sealed or unsealed),
and pressures, cooling time, screw backpressure and rotation to optimize cycle time.
and pressures, cooling time, screw backpressure and rotation to optimize cycle time.
Conduct a pressure-loss study until you see
the fill pattern is reasonable, there are no air traps,
all cavities are reasonably balanced in filling, and the entire flow path, sprue, runner, and gate show
reasonable pressure drops. (OK, a bit too perfect, but ...)
all cavities are reasonably balanced in filling, and the entire flow path, sprue, runner, and gate show
reasonable pressure drops. (OK, a bit too perfect, but ...)
Challenge the process with different colors
and/or lots of material or 100% regrind to make sure the
process still makes acceptable parts.
process still makes acceptable parts.
Run parts until they not only look good but
pass all initial quality and function tests to prove they are
good.
good.
Document the process with plastic variables
not machine setpoints. For example, document fill
time—not in./sec or mm/sec injection speed. That is, you fill the part to 95% full by volume in
1.25 sec, with weight and a picture of the fill-only part (no packing). You do not document a velocity
setpoint. Use whatever velocity gives you the 1.25-sec fill time. Do not set out to duplicate machine
setpoints—replicate plastic conditions.
time—not in./sec or mm/sec injection speed. That is, you fill the part to 95% full by volume in
1.25 sec, with weight and a picture of the fill-only part (no packing). You do not document a velocity
setpoint. Use whatever velocity gives you the 1.25-sec fill time. Do not set out to duplicate machine
setpoints—replicate plastic conditions.
So now you have done your homework, your
parts have passed inspection, and production is not
scheduled for another week. So where is Murphy? He’s looming. Murphy often likes to wait until
production starts before he shows up. How many times have you seen this play out? Initial parts
passed your customer’s inspection and testing. Everything is fine, even as production starts. Maybe
even the first production run goes off without a hitch. Then, orders ramp up and the tool is now
running more frequently, perhaps on different machines. Suddenly, parts are out of specification and
Crusty Sr. (he’s the lead processor) cannot bring the process back in line. What did we miss?
scheduled for another week. So where is Murphy? He’s looming. Murphy often likes to wait until
production starts before he shows up. How many times have you seen this play out? Initial parts
passed your customer’s inspection and testing. Everything is fine, even as production starts. Maybe
even the first production run goes off without a hitch. Then, orders ramp up and the tool is now
running more frequently, perhaps on different machines. Suddenly, parts are out of specification and
Crusty Sr. (he’s the lead processor) cannot bring the process back in line. What did we miss?
Once you have set the process and the cycle
is optimized, start watching the entire part temperature,
or thermal image of the part, as you are molding.
or thermal image of the part, as you are molding.
Injection molding is a thermal cycle, and
some molds can take a long time to equilibrate. The energy
going in with the hot melt and out via the cooling system(s) has to balance, and this process often
takes longer than anyone likes. It is one of the reasons I dislike some aspects of just-in-time inventory
control—nobody considers thermal stabilization time. Some molds take several hours to equilibrate.
As they change in temperature, the parts will change as shrinkage rates change. This is especially
true for high-shrink resins like PP. So how do you tell if your process is stable and will run well in
production?
going in with the hot melt and out via the cooling system(s) has to balance, and this process often
takes longer than anyone likes. It is one of the reasons I dislike some aspects of just-in-time inventory
control—nobody considers thermal stabilization time. Some molds take several hours to equilibrate.
As they change in temperature, the parts will change as shrinkage rates change. This is especially
true for high-shrink resins like PP. So how do you tell if your process is stable and will run well in
production?
You must monitor part temperature via
infrared (IR) thermal imaging. Once you have set the process
and the cycle is optimized, start watching the entire part temperature, or thermal image of the part,
as you are molding. One-spot measurement is not as effective.
and the cycle is optimized, start watching the entire part temperature, or thermal image of the part,
as you are molding. One-spot measurement is not as effective.
Make sure you always take the IR image the
same amount of time after ejection or mold open.
Take an IR picture of the part or parts while they are on the robot or laid out after ejection.
The sooner you get the image, the better.
Take an IR picture of the part or parts while they are on the robot or laid out after ejection.
The sooner you get the image, the better.
Want to learn more? Visit Injection Molding
Know How.
If it is a multi-cavity tool, you will be
amazed at how much you can learn by looking at all the
parts in one picture. Are they all the same temperature? If not, you need to investigate why.
parts in one picture. Are they all the same temperature? If not, you need to investigate why.
Check out the thermal image on p. 36. The
parts may look the same visually, but I guarantee you
they are not all the same size, and performance will not be identical. Parts coming out of the mold
at different temperatures will not be the same or function the same.
they are not all the same size, and performance will not be identical. Parts coming out of the mold
at different temperatures will not be the same or function the same.
Normally, once a process starts, the mold
warms as heat is transferred from the molten plastic to
the steel of the mold. Water temperature may not change much (in vs. out should be less than
2° C or 4° F), but the steel temperature does change and there may be hot spots or areas that are
not cooled well due to cooling line location issues. The thermal-image profile reflects what is
happening in the mold steel.
the steel of the mold. Water temperature may not change much (in vs. out should be less than
2° C or 4° F), but the steel temperature does change and there may be hot spots or areas that are
not cooled well due to cooling line location issues. The thermal-image profile reflects what is
happening in the mold steel.
Also, track the pressure or integral under
the pressure curve at transfer. As a mold starts up, usually
the pressure at transfer will trend up or down for a number of shots. If the mold is heating up or
cooling down, it is difficult to get a reading on steel temperature, but IR camera technology allows
fast and easy monitoring of the molded parts.
the pressure at transfer will trend up or down for a number of shots. If the mold is heating up or
cooling down, it is difficult to get a reading on steel temperature, but IR camera technology allows
fast and easy monitoring of the molded parts.
Bottom line: Watch part temperature and
pressure at transfer for trends. Start saving parts when these
process parameters stop trending. In addition, check periodically that they are within the normal range.
process parameters stop trending. In addition, check periodically that they are within the normal range.
sourced
from:https://www.ptonline.com/columns/injection-molding-new-mold-trialwill-it-run-247